Clinical Research Bldg at Florida Hospital's Health Village Campus General Conditions Estimate 12/21/2016
General Requirements - Project Staffing (Shell)
Total Cost
QTY DUR Unit Cost
Total Cost
Labor
Other
Burden Factor $19,680 0.4
Senior Project Manager
41 41
WK $3,000 WK $2,000
$49,200 $82,000
$68,880 $114,800 $5,500 $6,000 $2,000 $88,970 $5,500 $6,000 $2,000 $74,620 $5,500 $5,000 $2,000
Superintendent - Core, Shell and Site
$32,800
Living / Per Diem / Misc Vehicle Allowance
10.0 MO $550 10.0 MO $600 10.0 MO $200 10.0 MO $550 10.0 MO $600 10.0 MO $200 10.0 MO $550 10.0 MO $500 10.0 MO $200 41 WK $1,550 41 WK $1,300
$5,500 $6,000 $2,000 $5,500 $6,000 $2,000 $5,500 $5,000 $2,000
Cellular Phone
Project Engineer - Core, Shell and Site
$63,550
$25,420
Living / Per Diem / Misc Vehicle Allowance
Cellular Phone
Construction Admin - Core, Shell and Site
$53,300
$21,320
Living / Per Diem / Misc Vehicle Allowance
$0
Cellular Phone Superintendent - TI
0
WK $2,000 MO $550 MO $600 MO $200 WK $1,550 MO $550 MO $600 MO $200
$0
$0
$0 $0 $0 $0 $0 $0 $0 $0
Living / Per Diem / Misc Vehicle Allowance
0.0 0.0 0.0 0.0 0.0 0.0 0
$0 $0 $0
Cellular Phone
Project Engineer - TI
$0
$0
Living / Per Diem / Misc Vehicle Allowance
$0
Cellular Phone
$0
Subtotal - Project Staffing
$386,770
$248,050 $39,500 $99,220
QTY DUR Unit Cost Total Cost General Requirements - Staff Support and Logistics
Total Cost
Labor
Material
Equip. $7,500 $5,000 $1,500 $1,250 $1,100 $1,500 $3,850 $2,000 $2,550 $3,000 $750 $0
Sub
Office Trailer - Rental
10
MO $750 LS $5,000 MO $150 MO $125 LS $1,100 MO $150 MO $385 MO $200 LS $2,550 MO $300 EA $300 MO $120 MO $80 LS $750 MO WK $35
$7,500 $5,000 $1,500 $1,250 $1,100 $1,500 $3,850 $2,000 $2,550 $3,000 $1,435 $750 $0
Office Trailer - Delivery & Removal Office Trailer - Stair Setup Office Trailer - Electrical Hook-up Office Trailer - Electrical Consumption Office Trailer - Water Hook-up Office Trailer - WaterConsumption Office Trailer - Housekeeping
1
10
1
10
1
10
Office Trailer - Holding Tank
10 10 10 41 10 10 1 4
Office Supplies
Office Equipment & Furniture Internet and VoIP Phone Postage & Delivery Service Initial Reprographics Drinking Water Service Progress Photos - Drone
$1,435 $1,200 $1,200 $20,000 $3,500 $800
$1,200
$800
Temporary Fence (chain link w/screen)
2500 LF
$8
$20,000 $3,500 $56,935
MOT Plan
1
LS $3,500
Subtotal - Staff Support and Logistics
$0
$28,135 $30,000
Page 1